Neighborhood Notes

North Loop Reconstruction & Pedestrian Improvements – August 30

North Loop Reconstruction & Pedestrian Improvements

The North Loop Reconstruction & Pedestrian Improvements Project consists of two separate projects:

  1. A full street reconstruction along 3rd St N between 10th Ave N and 5th Ave N
  2. A pedestrian improvement project generally bounded by 10th Ave N on the north, 1st Ave on the south, West River Parkway on the east, and 4th St N on the west

North Loop Reconstruction Updates

8th Ave N Sidewalk8th Ave N Parking Bays3rd St N Grading for Paving

WORK THIS PAST WEEK

5th Ave N

  • Began driveway placement
  • Began installing curb and gutter
  • Began installing light bases
  • Continued installing conduit for lights
  • Placed the second lift of asphalt from 4th St N to Washington

7th Ave N

  • Continue work on the north side of Washington

8th Ave N

  • Grading for walks and driveways
  • Continued sidewalk placement
  • Continued placing driveways
  • Continued work on the north side of Washington
  • Started placing parking bays

9th Ave N

  • Continued placing driveways
  • Continued placing sidewalks
  • Continued work on the north side of Washington

3rd St N

  • Finished amending poor soils between 8th and 10th Aves N
  • Finished grading and bringing in aggregate in preparation for paving
  • Placed the first lift of asphalt from 5th Ave N to 6th Ave N
  • Continuing the underground utility work
  • Began relocating power poles

WORK ANTICIPATED FOR THE REMAINDER OF THIS WEEK AND NEXT WEEK

5th Ave N

  • Continue with driveway placement
  • East side sidewalk placement
  • Continue with light foundation installation
  • Remove globe lights on the east side of 5th Ave N

7th Ave N

  • Place the 3rd lift of asphalt either 7-30 or 8-4
  • Finish placing driveways
  • Continue work on the north side of Washington

8th Ave N

  • Finish placing sidewalks
  • Finish placing driveways
  • Continue work on the north side of Washington

9th Ave N

  • Continue placing driveways
  • Continue placing sidewalks
  • Continue work on the north side of Washington

3rd St N

  • Complete underground utility work
  • Placement of the first lift of asphalt is tentatively planned between 8-30 and 9-4
    • 6th Ave N to 7th Ave N Currently paving this
    • 7th Ave N to 10th Ave N -Hoping to finish this stretch today 8-30, if not will continue next week
  • Installation of curb and gutter will follow asphalt placement

For more information on this project, visit the project website.


North Loop Pedestrian Improvements Updates

Crews will be coming back in September to finish up the job.

WORK THIS PAST WEEK

  • 1ST St N & 4th Ave –Finished water work
  • 2ND St N and 3rd Ave N – Continuing sewer work

REMAINING WORK ON THIS PROJECT WILL START UP AGAIN ON 9-9-19

1ST St N

  • 2nd Ave SE corner
  • 4th Ave SE and NE corner

2nd St N

  • 1st Ave N – All corners
  • 2nd Ave N – NE, SE and SW
  • 3rd Ave N – All, currently the City is working in this intersection, pedestrian ramps will be done after the sewer work is complete
  • 5th Ave N – SE corner
  • 8th Ave N – South side and NE corner
  • 10th Ave N – SE and SW corners

4th St N

  • 10th Ave N – NE corner
  • 7th Ave N – South side

Other

  • All signal installation will start late in September due to long lead times on materials
  • Remaining concrete work will continue through September

For more information on this project, visit the project website.

Miscellaneous

Stakeholder Meeting –These meetings are informal, held biweekly and intended to offer residents and businesses on the job an opportunity to get construction updates, ask construction and access related questions.

 

Date/Time:         September 4, 7:30 am to 8:30 am

Location:           Corner Coffee 514 N 3rd St #102, Minneapolis MN 55401

As always, feel free to contact myself (612-673-3365) or John Benjamin (651-443-1096) with any construction related questions or concerns.


Contact Information

Project Manager:

Stephanie Malmberg, stephanie.malmberg@minneapolismn.gov, 612-673-3365

Chief Field Inspector:

John Benjamin, john.benjamin@minneapolismn.gov, 651-443-1096


For reasonable accommodations or alternative formats please contact Stephanie Malmberg at 612-673-3365.

People who are deaf or hard of hearing can use a relay service to call 311 at 612-673-3000. TTY users can call 612-673-2157 or 612-673-2626.

Para asistencia 612-673-2700, Yog xav tau kev pab, hu 612-673-2800, Hadii aad Caawimaad u baahantahay 612-673-3500.

www.minneapolismn.gov/publicworks